Ireland urgently needs a modern rail traffic management system.
The existing control technology is approaching the end of its supported life, while planned increases in rail frequency and capacity depend on having a reliable system capable of safely managing additional train movements. The proposed replacement was intended to become a critical component of the new National Train Control Centre at Heuston Station.
Instead, Iarnród Éireann is proposing to write off approximately €50 million connected to a system that has not been successfully deployed.
The original target cost for the traffic management system was reportedly €19.5 million. The contract was awarded to the Spanish technology company Indra in 2020 and was initially expected to be completed by June 2024. By 2026, however, testing had concluded that the software was not suitable for deployment on the Irish rail network. (Source)
The proposed €50 million write-down reportedly includes approximately €28 million in design and software costs and another €17 million in project-management costs directly associated with the Indra system. Certain other expenditure, including the National Train Control Centre building, will not be written off because it can still be used with a replacement system. (Source)
It is tempting to describe this as another example of an Irish public body failing to develop its requirements before tendering a major project.
The available evidence suggests that the failure was more complicated—and potentially more instructive—than that.
The central problem may not have been the absence of written requirements. It appears to have been the failure to establish whether the supplier’s proposed product actually existed in a mature, supportable form and could demonstrably satisfy those requirements without extensive new development.
In other words, there may have been plenty of documentation but insufficient verification.
What was Irish Rail trying to buy?
Iarnród Éireann was seeking a traffic management system that could regulate train movements across the network and support the transition from the existing Central Traffic Control Centre at Connolly Station to a new National Train Control Centre at Heuston Station.
The system was intended to improve how the railway manages:
- train movements;
- signalling information;
- disruption and recovery;
- operational decision-making;
- timetable execution;
- network capacity;
- and future service expansion.
This was not an ordinary administrative IT system. It was a safety-critical operational platform that would sit at the centre of Ireland’s railway infrastructure.
The procurement process began with market engagement in 2015. A formal competition was launched in 2018, and two bids were received in 2019.
According to Iarnród Éireann, bidders were expected to demonstrate that their existing products could satisfy at least 70% of the requirements without additional software development. The purpose of that condition was obvious: the State wanted to acquire a mature system rather than finance the development of an experimental new product.
Indra submitted a 242-page requirements-compliance document indicating that its proposed system met approximately 96% of the contractual requirements. That compliance matrix was incorporated into the contract.
Indra also referred to a 15-year history involving 21 deployments across different national railway systems. This led Iarnród Éireann to believe that the proposed DaVinci 2.0 system was a developed and mature product that could be introduced in Ireland with relatively limited additional development. (Source)
On paper, therefore, the procurement may have looked relatively strong.
There was a long specification, a substantial compliance matrix, external advisers and references to previous international deployments.
Nevertheless, the project failed.
The product changed after the contract was awarded
One of the most important developments occurred early in the preliminary design stage.
Indra informed Iarnród Éireann that the version of the product used to support its bid—including the version deployed in Lithuania—would not remain supportable for the duration of the proposed maintenance contract.
Instead, the Irish project would move to a newer generic product.
That product was still being developed.
Iarnród Éireann has since stated that, to its knowledge, the newer generic product has not been successfully deployed on any railway. Despite this, the project team, supported by external advisers, concluded at the time that Indra’s revised approach remained compliant with the contract. (Source)
This may be the most consequential decision in the entire project.
The procurement had been designed to avoid excessive new software development. Bidders were required to demonstrate that most of the necessary functionality already existed.
Yet the State appears to have found itself relying on a newer product that was still under development.
That should have triggered a fundamental reassessment:
Was Ireland still receiving the product evaluated during the competition, or had the State effectively become an early customer financing the development of a substantially new platform?
A mature product requiring limited configuration is a very different procurement risk from a generic platform that is still being built.
The commercial terms, testing strategy, payment milestones and allocation of risk should have reflected that difference.
Were the requirements incomplete?
Indra has argued that the project was not sufficiently specified from the beginning. Iarnród Éireann disputes this and points to its detailed requirements, technical reviews and the contractual compliance matrix.
The complete contractual and technical records have not yet been independently examined in public. It is therefore too early to determine precisely how responsibility should be divided between:
- Iarnród Éireann;
- the National Transport Authority;
- Indra;
- external project-management advisers;
- systems-integration advisers;
- safety-assurance advisers;
- and the wider governance structures surrounding the project.
However, it is important to distinguish between several different issues that can easily be grouped together under the general heading of “poor requirements”.
A project can fail because:
- the buyer did not know what it needed;
- the requirements were incomplete or ambiguous;
- the supplier misunderstood the requirements;
- the supplier overstated the capability of its product;
- the product evaluated during procurement was later replaced;
- existing functionality turned out to require new development;
- buyer requirements changed substantially during delivery;
- interfaces and dependencies were not properly understood;
- testing occurred too late;
- or governance failed to respond when the warning signs emerged.
These are different failure modes. Each requires different controls.
A 242-page specification does not necessarily mean that the requirements were good. At the same time, a failed project does not automatically prove that the requirements were absent.
The key question is whether each major requirement was complete, testable, traceable and verified against a functioning product before the State assumed substantial financial exposure.
Paper compliance is not demonstrated compliance
Indra reportedly claimed that its proposed system met 96% of the contractual requirements.
That figure sounds reassuring, but it raises another question:
How was compliance established?
A supplier completing a compliance matrix is not the same as a product successfully performing the required functions.
For a major safety-critical system, the word “compliant” should be divided into several categories:
| Classification | Meaning |
|---|---|
| Demonstrated | The function has been witnessed operating successfully |
| Live standard product | The function exists in the current supported version used by other customers |
| Configurable | The function can be delivered through documented configuration |
| Adaptation required | The function exists but requires changes for Ireland |
| New development | The function does not currently exist |
| Roadmap commitment | The supplier expects to build it in the future |
| Unverified | The buyer has not independently confirmed the claim |
A supplier may describe all seven categories as “compliant”, even though they expose the buyer to radically different levels of risk.
If a large portion of the claimed 96% depended on future development, adaptation, undocumented configuration or a product version that was about to be replaced, the headline percentage would have given a misleading impression of readiness.
The procurement process should have required evidence behind every important claim.
For high-risk functions, that evidence could have included:
- demonstrations using working software;
- verification at a live railway installation;
- executable prototypes;
- independent architecture reviews;
- representative Irish signalling scenarios;
- interface testing;
- performance testing;
- safety documentation;
- and direct contact with the railway operators cited as references.
The State should not have had to wait years to discover whether the underlying product could apply fundamental Irish signalling principles.
Testing came far too late
By 2023 and 2024, the project was experiencing delays and confidence in delivery was declining.
The programme was eventually restructured around a minimum viable product divided into eight commissioning phases.
By mid-2025, however, the software had failed signalling-principles testing. Indra’s own safety assessor reportedly concluded that the system was not ready to enter service.
Even the first commissioning phase—representing approximately 3% of the overall scope and covering a comparatively straightforward section of the railway—was delayed by a further 16 months.
In April 2026, another software release reportedly continued to exhibit many of the same systemic problems. Iarnród Éireann concluded that the product remained under development, that there was no credible commissioning programme and that the software was not fit for deployment. (Source)
More recent testing was reported to have definitively confirmed that the supplier would not achieve the committed commissioning milestones and that the software was not suitable for rollout on the Irish rail network. (Source)
The most troubling aspect is not simply that the software failed.
Software projects encounter problems. Complex railway systems require adaptation, integration and extensive testing.
The more important question is why fundamental product limitations were not exposed much earlier, before so much money had been spent.
A project of this type should have contained early tests designed to answer the most dangerous questions first:
- Can the system correctly model the Irish rail network?
- Can it apply Irish signalling principles?
- Can it integrate with existing infrastructure?
- Can it operate safely under representative conditions?
- Can it process the required volume of information?
- Can it recover safely when components fail?
- Is the proposed product version stable and supportable?
- Does the supplier have a credible route to safety approval?
If these questions cannot be answered during an early prototype or pilot, the project should not move into large-scale implementation.
Re-baselining can conceal rather than solve failure
The original planned completion date was June 2024.
As delivery problems emerged, the project was restructured and new milestones were agreed. In December 2024, the parties entered a revised commercial arrangement.
There may have been valid reasons to provide the supplier with an opportunity to remediate the project. Terminating a safety-critical technology contract is not a simple decision. It can result in litigation, further delays and the immediate need to procure a replacement.
However, re-baselining also creates a governance risk.
When an original budget or deadline becomes unachievable, management can replace it with a new target. The project then appears to be performing against the new baseline even though it has failed against the original commitment.
Every proposed re-baseline should therefore require a formal independent assessment:
- What has actually been completed?
- Which functions have been demonstrated?
- Why did the previous plan fail?
- What has materially changed?
- What evidence shows that the revised plan is achievable?
- How much additional money is at risk?
- What is the maximum remaining exposure?
- Is continuing more economical than termination and replacement?
- Who is accepting the additional risk?
The original baseline should never disappear from project reporting.
A public dashboard should continue to display the original cost, original completion date and original scope beside every subsequent revision.
The warning signs were visible
The problems with the contract had reportedly been known for several years. From the summer of 2025, the National Transport Authority was meeting Indra and Iarnród Éireann every two weeks.
Iarnród Éireann subsequently recommended that the contract be terminated and that an alternative plan be considered. NTA representatives acknowledged that termination was a major step because it could lead to litigation. (Source)
This illustrates one of the recurring problems with large public projects.
Once substantial money has been spent, terminating a project becomes politically, operationally and legally difficult. Decision-makers may continue investing because they hope that one more redesign, revised deadline or commercial settlement will rescue the original investment.
This is the sunk-cost problem.
The correct decision is not based on how much has already been spent. It should be based on whether the expected value of continuing is greater than the expected value of stopping and pursuing an alternative.
That decision becomes easier when the contract establishes clear termination points before the project begins.
How the Finmestro procurement model could have helped
The failure cannot be solved merely by telling public bodies to “write better tenders”.
A sophisticated procurement system must control the entire lifecycle:
- defining the problem;
- assessing internal capability;
- developing requirements;
- testing the market;
- verifying supplier claims;
- selecting the supplier;
- managing delivery;
- approving changes;
- releasing payments;
- tracking performance;
- and deciding whether to continue or terminate.
The Finmestro procurement model would introduce a structured workflow with controls proportionate to the cost, complexity and public importance of the project.
For the rail traffic management system, the following controls would have been particularly important.
1. A mandatory requirements-readiness gateway
The project should not have been allowed to proceed to full tender merely because a long specification had been produced.
Before publication, an independent review should have confirmed that the requirements were:
- sufficiently complete;
- clearly written;
- prioritised;
- internally consistent;
- technically feasible;
- connected to operational needs;
- linked to acceptance tests;
- and supported by named business owners.
Each requirement should have included:
- a unique reference number;
- the operational reason for the requirement;
- the responsible owner;
- its safety classification;
- its priority;
- affected systems and interfaces;
- the evidence required from the supplier;
- and the test that would determine whether it had been delivered.
A project can have hundreds of pages of documentation and still lack testable requirements.
The gateway should measure the quality and testability of the requirements, not the number of pages.
2. Independent buyer-side specialists
Public bodies should not rely exclusively on the supplier to explain whether the supplier’s product is suitable.
For a safety-critical railway system, the buyer needs its own experts in:
- railway operations;
- signalling;
- traffic management;
- software architecture;
- systems integration;
- cybersecurity;
- safety assurance;
- procurement;
- commercial negotiation;
- and project delivery.
Iarnród Éireann did engage external project-management, integration and safety advisers. The unresolved question is whether those advisers had sufficient authority, independence and accountability to challenge the product-maturity assumptions underlying the project.
The system should record:
- who reviewed each major claim;
- what evidence they examined;
- what conclusion they reached;
- what risks they identified;
- and who formally accepted those risks.
“External experts reviewed it” should never be the end of the audit trail.
A reviewer should be identifiable and their reasoning should be recorded.
3. Exact product-version verification
Suppliers should be required to state precisely what they are offering.
This should include:
- product name;
- version number;
- release date;
- support period;
- current customers;
- live deployments;
- functionality used at each deployment;
- safety approvals;
- known limitations;
- required adaptations;
- and functionality that does not yet exist.
The contract should prohibit a material substitution of the evaluated product without a new approval process.
If a supplier announces after contract award that the evaluated version will become unsupported and must be replaced with a newer product still under development, the platform should automatically trigger a major project gateway.
The decision-makers would then have to determine whether:
- the new product remained equivalent;
- the original competition remained valid;
- the commercial terms should be revised;
- additional guarantees were necessary;
- a new prototype was required;
- or the procurement should be reconsidered.
A change of this magnitude should not be processed as an ordinary design decision.
4. Direct verification of reference projects
Supplier case studies should not be accepted without independent verification.
The buyer should contact previous customers directly and ask:
- Which product version was deployed?
- Which functions are live?
- How much custom development was required?
- Was the original deadline met?
- Was the original budget met?
- How many critical defects occurred?
- Did the product achieve safety approval?
- How responsive was the supplier?
- What would the customer do differently?
- Would the customer select the same supplier again?
Where the supplier relies on a particular international deployment to establish product maturity, the buyer should inspect that deployment or commission an independent technical assessment.
The State should verify that the referenced system is genuinely comparable to the system being offered.
5. A paid competitive proof-of-capability stage
Before awarding the entire contract, shortlisted suppliers could have been paid to demonstrate their systems using representative Irish data and operational scenarios.
The proof-of-capability stage could have required each bidder to:
- model a defined section of the Irish rail network;
- ingest representative timetable and infrastructure data;
- demonstrate key signalling principles;
- interface with sample existing systems;
- manage a disruption scenario;
- demonstrate system recovery;
- show controller workflows;
- provide performance and resilience results;
- identify all required new development;
- and demonstrate the exact product version proposed for delivery.
The State would incur an upfront cost, but that cost would be insignificant compared with writing off €50 million.
Proof-of-capability stages are particularly valuable where only a small number of suppliers operate in the market and where documentary claims are difficult for a non-specialist evaluation panel to verify.
6. A product-maturity score
The evaluation should not treat all claimed functionality as equivalent.
A product-maturity score could allocate different values to:
- functionality already operating in a comparable live environment;
- standard functions in a supported release;
- documented configuration;
- minor adaptation;
- major adaptation;
- new software development;
- and future roadmap commitments.
For example, a demonstrated live function could receive full credit, while a roadmap promise might receive little or no credit.
The evaluation would then reveal how much of the system actually existed at the time of the bid.
This would prevent a supplier from achieving a headline compliance score based largely on functions that had not yet been built.
7. Milestone payments tied to working software
Payments should be linked to accepted operational outputs, not merely to the passage of time or the production of documents.
Potential payment gates could include:
- agreed architecture;
- successful network modelling;
- demonstrated interfaces;
- core signalling tests passed;
- cybersecurity testing completed;
- safety documentation accepted;
- pilot system operating in shadow mode;
- independent safety approval;
- controller training completed;
- operational acceptance;
- and successful commissioning.
The contract should limit the percentage of the total value payable before the supplier demonstrates that the fundamental architecture works.
For example:
No more than 10% to 15% of the development price should be released before the supplier successfully demonstrates the core safety, signalling and integration functions using representative Irish scenarios.
This would not necessarily prevent failure, but it would cap the taxpayer’s exposure.
8. A small but representative pilot
The first live deployment should be sufficiently small to control risk but sufficiently representative to test the difficult parts of the system.
A pilot that covers only the easiest 3% of the scope may fail to test the interfaces and operational complexity that create the greatest risk.
The pilot should include enough complexity to answer whether the system can genuinely scale across the network.
The full rollout should not begin until the pilot has:
- passed acceptance testing;
- received the required safety approval;
- operated successfully for a defined period;
- demonstrated recovery from failure;
- and been independently signed off.
9. A permanent requirements and change-control register
The dispute over whether the project was adequately specified demonstrates the importance of maintaining a complete requirements history.
The Finmestro platform would record:
- the original requirement;
- the supplier’s tender response;
- the evidence supporting the response;
- the evaluation score;
- the final contractual commitment;
- subsequent clarifications;
- proposed changes;
- the reason for each change;
- whether the change was genuinely new;
- its effect on cost and timing;
- and the person who approved it.
This would make it possible to establish whether a disputed item was:
- included in the original scope;
- reasonably implied by the original requirement;
- a clarification;
- a response to a supplier defect;
- or a genuinely new buyer request.
Without this traceability, the buyer can accuse the supplier of failing to deliver while the supplier claims that the buyer continually changed the scope.
A reliable change log converts that argument into evidence.
10. Automatic stop-and-review triggers
A major project should automatically enter independent review when certain conditions arise.
Triggers could include:
- replacement of the proposed product version;
- failure of a safety-critical test;
- repeated missed milestones;
- a material increase in expected cost;
- a material delay in commissioning;
- movement of functionality from “existing” to “new development”;
- failure to produce a credible delivery plan;
- deterioration in supplier financial health;
- or loss of confidence by the buyer’s technical team.
The review would recommend one of three outcomes:
- continue;
- remediate under revised controls;
- terminate and replace.
Continuing would require explicit approval supported by objective evidence.
The project should not be allowed to drift from one revised plan to another without a formal decision.
11. Transparent re-baselining
Every revised project plan should retain the original baseline.
The public project page could display:
- original approved cost;
- current forecast cost;
- original completion date;
- current expected completion date;
- original scope;
- functions demonstrated;
- functions remaining;
- money paid;
- current risks;
- failed milestones;
- approved changes;
- and responsible decision-makers.
This prevents failure from being obscured by repeatedly replacing the targets against which performance is measured.
A project that was originally supposed to finish in June 2024 should not be described as “on track” in 2025 simply because a new date was agreed.
12. Supplier-performance profiles
Finmestro would maintain a performance history for suppliers participating in public procurement.
The profile could include:
- original and final project costs;
- original and final delivery dates;
- acceptance-test results;
- disputes;
- settlements;
- terminations;
- product substitutions;
- reference checks;
- change-request patterns;
- and verified feedback from other public bodies.
The record should follow the wider corporate group and beneficial owners where appropriate, rather than being limited to the specific subsidiary that signed the contract.
This would allow future buyers to see whether a supplier has repeatedly:
- missed deadlines;
- understated development requirements;
- relied on excessive change requests;
- replaced products after award;
- or failed acceptance testing.
Public bodies currently risk learning the same lessons separately. A central supplier profile would allow the State to retain institutional knowledge.
13. Clear accountability on the buyer side
Major public projects often involve numerous boards, committees, agencies, advisers and consultants.
This can create a situation in which many parties participate but no individual is clearly accountable for the final decision.
For each major risk, the platform should identify:
- the person responsible for assessing it;
- the person responsible for managing it;
- the evidence relied upon;
- the person authorised to accept it;
- and the date on which it was accepted.
For the rail project, this could include named accountability for:
- requirements completeness;
- product maturity;
- architecture;
- safety;
- integration;
- commercial management;
- testing;
- project delivery;
- and the decision to continue after missed milestones.
Accountability does not mean blaming individuals whenever a project encounters difficulty.
It means ensuring that significant decisions have identifiable owners and documented reasoning.
14. Cost transparency
Suppliers should be required to submit costs in a standardised structure rather than a single overall amount.
This could include:
- role;
- skill set;
- location;
- daily rate;
- expected number of days;
- software licences;
- hardware;
- subcontractors;
- travel;
- project management;
- testing;
- safety assurance;
- maintenance;
- and contingency.
The rail write-down reportedly includes a substantial amount of project-management expenditure in addition to design and software costs. Standardised cost reporting would make it easier to see how expenditure was building up and whether the level of management and advisory cost remained proportionate to demonstrable delivery. (Source)
15. Lessons must become controls
Public bodies regularly conduct reviews after projects fail.
The problem is that the findings often become reports rather than operational controls.
The National Transport Authority has commissioned an independent review into the failed system, reportedly costing approximately €225,000. The review is expected to examine the procurement, governance and management of the project. (Source)
The value of that report will depend on what happens next.
Each finding should be converted into:
- a mandatory workflow step;
- an approval requirement;
- a standard contract term;
- a project-warning trigger;
- a template;
- a supplier-performance record;
- or an automated control.
If a review concludes that product maturity was not adequately verified, future technology procurements should be unable to proceed without product-maturity evidence.
If it concludes that testing happened too late, future projects should require an early proof-of-capability stage.
If it concludes that accountability was unclear, future platforms should require named owners before approval.
That is how lessons are institutionalised.
What the procurement process should have looked like
A stronger workflow for the rail traffic management system might have been:
Stage 1: Define the problem
Document why the current system needs replacement, the operational outcomes required and the consequences of delay.
Stage 2: Map the current environment
Identify all existing signalling, telecommunications, timetable, infrastructure and operational interfaces.
Stage 3: Simplify where possible
Determine whether existing processes or interfaces can be standardised before attempting to digitise them.
Stage 4: Develop testable requirements
Assign each requirement an owner, priority, safety classification and acceptance test.
Stage 5: Conduct an independent requirements review
Confirm that the State has developed enough certainty to approach the market.
Stage 6: Assess the supplier market
Identify which products are genuinely operational on comparable railways and which would require substantial development.
Stage 7: Verify references
Contact railway operators directly and inspect comparable deployments.
Stage 8: Run a competitive proof of capability
Require shortlisted suppliers to demonstrate their products using representative Irish scenarios.
Stage 9: Evaluate delivery confidence
Score not only price and written compliance but also product maturity, comparable deployments, integration risk, safety readiness and dependence on new development.
Stage 10: Award a staged contract
Limit early expenditure and tie payments to objective technical outcomes.
Stage 11: Complete a representative pilot
Do not proceed to national rollout until the pilot has passed independent testing and safety approval.
Stage 12: Monitor through a live project page
Report milestones, spending, risks, changes and supplier performance against the original contract.
Stage 13: Trigger intervention automatically
Require an independent continue-or-terminate decision when critical tests fail or major milestones are missed.
Stage 14: Retain the lessons
Record supplier performance and convert the project findings into controls for future procurements.
The broader lesson for Irish public procurement
The central lesson is not simply that public bodies need to produce longer requirements documents.
Ireland already produces lengthy tenders, detailed specifications and complex contracts.
The more important requirement is to distinguish clearly between:
- what the State needs;
- what the supplier says it can provide;
- what the supplier’s current product demonstrably does;
- what still needs to be configured;
- what still needs to be developed;
- and how much public money can be spent before those uncertainties are resolved.
A compliance matrix is not a functioning system.
A supplier reference is not an independently verified deployment.
A product roadmap is not an existing feature.
A revised deadline is not evidence that a project has recovered.
A large project team is not the same as clear accountability.
And money already spent is not a reason to continue spending.
The principle at the centre of the Finmestro model should be simple:
No major technology contract should proceed on documentary compliance alone. Critical capabilities must be demonstrated, independently tested and connected to staged payments before the State assumes large-scale delivery risk.
This approach could not guarantee that every project would succeed. No procurement system can eliminate all technical and commercial risk.
It could, however, identify dangerous assumptions much earlier.
In the case of the rail traffic management system, it might have revealed before full contract award that the proposed product was less mature than it appeared. At a minimum, it could have limited the State’s exposure to the cost of a controlled prototype and pilot rather than allowing expenditure to grow towards €50 million before fundamental problems were conclusively established.
The independent review has not yet been completed, and it would be premature to make a final determination about responsibility.
However, the publicly available evidence already points to the need for stronger controls over:
- product verification;
- requirements traceability;
- early testing;
- product substitutions;
- milestone payments;
- project re-baselining;
- supplier performance;
- and buyer-side accountability.
Ireland did not merely buy software that failed.
It appears to have operated a procurement process in which critical uncertainty was allowed to survive for too long—and became extraordinarily expensive to resolve.